Update18 Aug 2026

Sobha One World Phase 1 Foundation Works Scheduled to Begin August 2026 per Karnataka RERA

Construction Milestone: Sobha One World Phase 1 Foundation Works Commence August 2026

Excavation and foundation works for Phase 1 (Wings 1 and 2) have begun in August 2026, marking the first major on-site construction milestone recorded in Karnataka RERA quarterly progress reports.

Timeline from Launch to Active Construction

Sobha One World officially launched on 13 June 2026 at the Grand Allotment Event in Hoskote, East Bangalore, with the pre-launch held on 5 June 2026 and the EOI window running from 10 May to 20 May 2026. Karnataka RERA approval of all 6 phases was granted on 8 May 2026 under Approved Plan No. STRRPA/TP/CC/652/2025-26/318.

Following the allotment process closure in June, the 48-acre One Residences parcel at Amanidoddakere Village, Hoskote underwent site mobilization ahead of the August 2026 foundation start. Final topographic and geotechnical surveys for Wings 1 and 2 (Phase 1) were completed ahead of the August 2026 foundation start date filed with Karnataka RERA.

Phase 1 Scope and Scale

Phase 1 covers 48 acres, known as Sobha One Residences, and includes 14 towers, each with a 3B + GF + 1F parking + 45/46 typical residential floor structure, making it one of the tallest residential developments in the Hoskote corridor. A total of 3,484 ultra-luxury apartments are planned across 6 RERA-registered sub-phases.

The project spans a 300-acre master plan with Phase 1 (One Residences) covering 48 acres. Sobha Limited owns 100% of the land with no joint development agreement and no co-developer involvement.

RERA Filing and Regulatory Transparency

Mandatory on-site signage was erected following the 8 May 2026 approval, displaying Approved Plan No. STRRPA/TP/CC/652/2025-26/318 and all six per-phase RERA registration numbers (PR/080526/008634 through 008639) as required under Section 11 of the RERA Act, 2016. All upcoming milestones are filed with Karnataka RERA and are legally binding under the Act, with buyers able to verify each milestone's progress through the Karnataka RERA quarterly progress reports portal once the project enters active construction.

Possession Timeline

Phase 1 possession is confirmed for 1 December 2032, within a 6-year construction timeline starting August 2026, with all possession dates legally registered with Karnataka RERA and binding under the Act. Phase-wise possession dates range from 31 August 2032 to 30 September 2033.

Sobha's Operational History and Presence

Sobha Limited, founded on 7 August 1995 by P.N.C. Menon, is one of India's top-tier listed real estate developers and the country's only fully backward-integrated real estate company. The company has delivered 500 plus projects across India.

Sobha's Bengaluru portfolio is the city's second-largest premium residential footprint after Prestige, with 200+ delivered projects covering approximately 68 million sqft. Sobha Limited started its work in Bangalore in 1995 and has now launched 30+ luxury projects in prime areas of the city.

The developer's primary differentiator is its unique backward integrated business model, managing architectural design, structural engineering, and interior manufacturing entirely in-house to ensure unmatched craftsmanship, strict quality control, and reliable project timelines.

Hoskote Corridor Context

Hoskote is located on the eastern side of Bangalore and is semi-urban, with new infrastructure and residential complexes appearing constantly. The Hoskote-Doddaballapur-Dabaspet stretch of the Satellite Town Ring Road is already operational, removing heavy vehicle traffic from local roads while providing a 35-minute traffic-free run to the Kempegowda International Airport.

The area has seen a 115% price appreciation over five years and is currently a top choice for investors due to the new Chennai Expressway and STRR connectivity. Hoskote is the core of the Aero-IT Corridor and the Narsapura Industrial Area (home to Honda, Volvo, and Mahindra).

Site Access and Monitoring

Buyers can visit the Hoskote site at any time to check ground progress, with the project address at Amanidoddakere Village, Kasaba Hobli, Hoskote, Bengaluru Rural, Karnataka 562114. Monthly site progress photos are updated regularly on the project's official construction status page.

Related: SOBHA ONEWORLD

← All updates

×
Express Your Interest